Pipe jacking construction must rely on the thrust of the main jacking oil cylinder, the pipeline room, and the intermediate jacking station

Pipe jacking construction must rely on the thrust of the main jacking oil cylinder, the pipeline room, and the intermediate jacking station

  • Categories:news
  • Author:
  • Origin:
  • Time of issue:2020-10-14 10:32
  • Views:

(Summary description)Pipe jacking construction is a non-excavation construction method, which is a construction technique for pipeline burying facilities without excavation or less excavation. Pipe jacking method construction is to overcome the pipe and the surrounding soil with the help of jacking equipment in the working pit, push the pipe into the soil according to the designed slope, and transport the earth away. After one section of the pipe has been jacked into the soil layer, the second section of the pipe will continue to be pushed. The principle is to push the tool pipe or roadheader from the working pit through the soil layer and hoist it in the receiving pit with the help of the thrust of the main top cylinder, the pipeline room, and the relay room. The pipeline is buried between the two pits immediately after the tool pipe or the tunneling machine.

Pipe jacking construction must rely on the thrust of the main jacking oil cylinder, the pipeline room, and the intermediate jacking station

(Summary description)Pipe jacking construction is a non-excavation construction method, which is a construction technique for pipeline burying facilities without excavation or less excavation.



Pipe jacking method construction is to overcome the pipe and the surrounding soil with the help of jacking equipment in the working pit, push the pipe into the soil according to the designed slope, and transport the earth away. After one section of the pipe has been jacked into the soil layer, the second section of the pipe will continue to be pushed.



The principle is to push the tool pipe or roadheader from the working pit through the soil layer and hoist it in the receiving pit with the help of the thrust of the main top cylinder, the pipeline room, and the relay room. The pipeline is buried between the two pits immediately after the tool pipe or the tunneling machine.

  • Categories:news
  • Author:
  • Origin:
  • Time of issue:2020-10-14 10:32
  • Views:
Information

Pipe jacking construction is a non-excavation construction method, which is a construction technique for pipeline burying facilities without excavation or less excavation.

Pipe jacking method construction is to overcome the pipe and the surrounding soil with the help of jacking equipment in the working pit, pushing the pipe into the soil according to the designed slope, and transporting the earth away. After one section of the pipe has been jacked into the soil layer, the second section of the pipe will continue to be pushed.

The principle of it is to push the tool pipe or roadheader from the working pit through the soil layer and hoist it in the receiving pit with the help of the thrust of the main jacking oil cylinder, the pipeline room, and the intermediate jacking station. The pipeline will be buried between the two pits immediately after the tool pipe or the tunneling machine end up the work.

Keyword:

Contact Information

E-mail:hannah@yzdilong.com

Address: Wujian Industrial Park, Jiangdu District, Yangzhou City, Jiangsu Province,China

Tel: +86 13852589366 / +86 13390658976

You can share with everyone